|
|
|
Figure 18. FOT Technology Installation, Operation, and Removal Schedule
|
|
|
Print  
|
|
Figure 18. FOT Technology Installation, Operation, and Removal Schedule| Participant | Hardware Installation Date | Hardware Removal Date |
|---|
| Dupre Transport | August - Week 4 | March - Week 1 | | Cox Petroleum | August - Week 4 | April - Week 1 | | Distribution Technologies | September - Week 1 | March - Week 5 | | Roadway Express | September - Week 3 | March - Week 3 | | Transport Service | September - Week 2 | March - Week 5 | | Quality Distribution | September - Week 3 | April - Week 1 | | Roeder Cartage | September - Week 4 | April - Week 2 | | R&R Trucking | September - Week 5 | April - Week 4 | | Dyno Transportation | October - Week 2 | May - Week 2 |
<Back to Chapter 4
|
|
|
|